Commissioning of the Pick-to-Light system

Here you will learn how the commissioning of a Pick-to-Light system proceeds in detail. You will learn how the system is prepared, started and technically commissioned.

Requirements for the Pick-to-Light commissioning

Before commissioning, the following work should be completed:

  1. Installation of the Pick-to-Light profiles including wiring. The connection terminals with the covers are not closed first.
  2. The individual compartment displays should not be built into the profiles at first.
  3. The Pick-to-Light controllers should be mechanically fixed and electrically connected. The plugs for the supply lines should not be plugged in at first.

1. the measurement of the wiring is carried out first

To perform the measurement, the terminals must first be accessible (no covers). The wiring of a Pick-to-Light system is not complicated and consists of only one 4-wire cable. However, the individual wires of the cable must be correctly connected to the appropriate terminal. The entire system is a BUS. If a fault should occur during installation and all displays are already installed, the fault is not easy to find (more about: Pick-to-Light Installation).

Measurements for short-circuits or interchanges should be taken at each terminal.

Measurements are made with a standard measuring device, e.g. continuity meter with a beep sound.
If a fault has been detected in the wiring, it must first be corrected, which is done very simply by exchanging the individual cores of the wiring.

2. switching on the controllers and installing the Pick-to-Light displays

Once all the wiring has been tested, the compartment displays can be installed and the connectors connected to the controllers.

We always switch on the controllers first and plug in the connectors. The voltage (24V) and the data signals on the Pick-to-Light rails are now present. Then the Pick-to-Light-subject displays are very simply clicked into the profiles at the corresponding positions. This is done without tools and without additional wiring.

Our tip: When clicking in the compartment displays, pay attention to the flashing LED of the piece count. If the display communicates with the controller, the dot of a 7-segment display flashes briefly.

Once all displays have been installed and reported to the control software, the electrical part of the commissioning is complete. Now the system can be configured. We describe the configuration in a separate article: Pick-to-Light Configuration.

3. installation of the covers and completion of commissioning

At the end of commissioning, the covers are clicked in place over the connection terminals for protection. In some installations, the spaces between the displays are also covered with lids. In principle, this is not necessary and may also have visual aspects.

Conclusion

Commissioning a Pick-to-Light system is not difficult, but should be done in a specific serial rim. First, check all the wiring. Only then switch on the controllers and click in the compartment displays. After that, the system can be configured.